CHAPTER 7 : PROJECT
CLOSEOUT
Introduction
Completing a project requires
procedures to closeout project contractual and administrative activities.
Role of the Organization in
Project Completion
Closing contractual activities requires the Relevant
body’s project manager to oversee final
settlement of project contracts, acceptance of contract deliverables,
collection of contract documents and records (such as as-built drawings,
operation and maintenance manuals, and warranties, etc.), and approval of final
payments. The project manager’s
responsibilities for administrative closeout relate to demobilizing the project
team and completing activities with other stakeholders, arranging the
disposition of project records, closing of funding and financing agreements,
and performing an evaluation of project success and lessons learned.
|
Construction
Contracts
|
|
|
|
|
|
The
project manager, commissioning manager,
construction manager/resident engineer (RE), and contract
|
|
|
administrator, should
follow the procedures
and actions specified
in each contract’s
terms and
|
|
|
conditions
to settle and close the project’s construction contract agreements.
|
|
|
For
a typical construction contract as project
manager, you will need to confirm the completion and acceptability
of the following activities :
|
|
|
Manuals and
Training
|
: The contractor
delivers the operations
and maintenance (O&M)
|
|
|
manuals for the
facilities
|
constructed and equipment installed and
provides any associated
|
|
|
training of Agency
staff in their use.
|
||
|
|
|
|
|
Beneficial Occupancy –
A contract is substantially complete when the permitting authority
|
||
|
issues a Certificate
of Beneficial Occupancy to the Agency and then the Agency can occupy
|
||
|
and begin use of the facility and
equipment.
|
||
CONTRACTUAL CLOSEOUT
|
Guaranties
and Warranties –
With beneficial occupancy confirm that the contractor has initiated
|
|
|
the
guaranties and warranties associated with the facility and equipment.
|
|
|
Record
or As-built Drawings – The construction manager(CM)/resident engineer(RE) confirms that the contractor has submitted the record drawings that show the as-built condition of the constructed facility and installed equipment.
|
|
|
|
Final Inspection –
Lead a final walk through inspection of the facility to confirm that the
contractor has completed the open punch list items and all work is
completed correctly and satisfactorily
Resolve Outstanding
Change/Claim Disputes – Project Manager
should make every effort to resolve any outstanding contract disputes so
that they do not drag on past contract and project completion.
Final Payment –
With the above activities satisfactorily completed you can approve the
final payment to the contractor and the Agency can close the contract.
Commissioning –
Assure that all other commissioning activities have been completed in a satisfactory
manner.
Professional Service
Contracts
Typical
closeout activities for a professional service contract include:
Verification of Scope
Completion –
Confirm that the professional service contractor has satisfactorily
delivered the services called for in the contract scope of work.
Contract Audit –
Where contract payments are on a cost plus fee basis, the contract
provisions should give the Agency the right to audit the contractor’s
costs. The audit should verify items such as direct labor rates, support for
time charges, support for other direct costs, and justification for overhead
rates
Final Payment and Release
of Retention – With scope completed satisfactorily and
audit completed, you can approve the final payment and release of any
retention held back from prior contract payments pending satisfactory
completion of services and audit of costs.
Project Demobilization
Managing the demobilization of the project can often test
the project manager’s administrative and
interpersonal skills in order to address the following end of project issues:
§ Key project staff that see the end of the
project coming and acquire positions elsewhere in the Relevant’s
Body’s before
their project role and duties are complete.
§ Or
the opposite, Relevant’s Body’s project staff whose duties are complete
and are difficult to relocate off
the project because there is no immediate
position for them to move to.
Professional service consultants, whose role is
concluding, prematurely transfer key staff to newer long term assignments
and/or endeavor to stretch out their services to maintain revenue.
To manage demobilization as project manager, you should develop a
staffing plan for the final phase of the project that plans the reduction in
the Relevant body’s own forces and those
of the professional service consultants. As project
Manager , You should work with the Relevant body’s human resources to help manage the transition
of staff off the project, ease their anxieties surrounding what their next role
is, and provide incentives for key staff to remain on the project and defer
moving on. Similarly,Project Manager
should meet with the principals of the professional service firms to reach
agreement on a timetable for winding down their services as the project
concludes.
The project
manager’s final challenge once the demobilization
plans are in place is to keep the project team’s attention
focused on the tasks needed to complete the project as opposed to what they
will be doing once the project is over.
Closure of Project
Financing and Funding
The project manager will need
to work with the Relevant body’s finance
staff to closeout the funding to the project,the Relevant body’s project responsibilities and work are
completed and the associated financial records closed.
Disposition of Project
Records
The project manager
has to arrange for project records to be transferred to the Relevant body’s document control function. Project records
required to be maintained will be determined by a combination of the Relevant
body’s own records retention policy,
retention requirements imposed by parties funding the project and any special
requirements due to contract provisions. Should there be an unresolved
change/claim dispute, it is important that all records pertaining to the
contract and dispute also be retained.
Project Evaluation
Before the project is over and key project staff
has dispersed, it is desirable for the project manager to hold a lessons
learned session. The lessons learned should focus on identifying project
strengths and weaknesses with recommendations on how to improve future
performance on projects. To be most effective the project
manager should encourage the project
team to identify and document lessons learned through the
project life cycle so that a database of lessons learned experience is built up
for consideration at the final lessons learned session. Lessons learned can
consider technical, managerial, and process
aspects of the project.
Stakeholder Closure
Perhaps
the most important aspect of completing the project is to achieve acceptance
and closure of the project by the project’s principal stakeholders, those who
sponsored the project, and those that are to use the facilities and equipment
delivered by the project. The Project
Authorization and PRD
documents formally set out the expectations for the project. The project manager should now receive formal
confirmation that with the hand over of the project deliverables from the
project team to the operational users, the project sponsors and users have
officially accepted the project deliverables.
This
formal acceptance is also the opportunity to celebrate project success with
some ceremony to mark the opening of the new facility and equipment into
operations.
(END OF THE CHAPTER)
Comments
Post a Comment