Chapter-6 : CONSTRUCTION

Chapter-6 : Construction


Introduction

Understanding,management of project construction by contractors, third parties, and the Relevant body’s is very important. Emphasis is placed on schedule, cost, and change controls; configuration management and document control; and partnering and value engineering (VE) incentives,Quality Assurance (QA) and Safety Management.
                                    

Role of the Organization in Construction

The Relevant body’s  project manager, to assure good performance during construction is to make timely and decisive decisions.Project organization and management approach, defined by the project management plan (PMP), should have clear lines of communication and delegated authority.

Role of the Construction Manager (Resident Engineer)

The organization will need project staff with expertise and experience in construction management beyond the capability and capacity of the Relevant body’s  regular employees, for which the Agency will need to retain a construction manager (CM) consultant. The CM acts as the Relevant body’s  representative with the contractors, oversees what work the contractors perform pursuant to the contract drawings and specifications, inspects the work as acceptable, and recommends payment of contractor invoices. The key CM staff is the resident engineer

Role of the Design Consultant(s) in Construction

Design consultant(s) who produced the contract drawings and specifications and ―sealed a‖ them with their professional engineering seal, are referred to as the designer(s) of record; and will continue to provide the following design services during construction:

# Receive and respond to construction contractor Requests for Information (RFI), communicated from the contractor to the designer through the CM. An RFI is a request by the contractor for clarification of the design intent of the drawings and specifications.
#   Review and recommend acceptance of contractor submittals called for in the drawings and specifications with respect to the construction deliverables.
#     Review change requests and estimate costs for change orders.

#  Make periodic visits to the site to assure design compliance and provide certification efforts as required by         the permitting organization.

Role of the Contractor in Construction

The role of the construction contractor is to:

#  Perform construction work defined by the contract drawings and specifications using means and methods that are the contractor’s responsibility.

#  Obtain the permits related to the work for which the contractor is responsible.

#  Develop and implement a quality control (QC) plan for inspection and testing of the work.

#  Develop and implement a safety plan to ensure a safe work site.
  

#   Deliver submittals defined by the contract drawings and specifications, such as

- Shop drawings, manufacturer’s drawings, calculations and data, and product information.

- Contract schedule updated monthly noting progress and looking ahead to upcoming work.


-Requests for payment supported by reports as called for in the contract. o Record drawings 

of the as-built work.

 # O&M manuals and training of Agency staff called for in the contract specifications.

 # Submit RFIs to the CM to obtain clarification of the design intent.

 #   Submit Requests for Change (RFC). 


    CONSTRUCTION MANAGEMENT

Project Organization for Construction

Figure 6-1 illustrates a project organization structure for construction for a project with three construction contracts (yellow boxes), where the Agency (blue boxes) has retained the services of a CM and a general engineering consultant (GEC) who is the designer of record (tan boxes). Delegation of authority for RFCs is illustrated by the ―red arrows and lines of communication for RFIs by ―green arrows.


Figure 6-1 - Project Organization, Assigned Authorities, 
and Lines of Communication for Construction





Agency Board




Board: Resolves changes above



GM's delegated authority

Agency

General Manager


Personnel

(GM)




GM: Resolves changes within



GM's delegated authority



Project




Manager   Project Manager: Resolves changes within



project manager's delegated authority




CM: Coordinates review of




RFIs and submittals by

Consultant


GEC; and resolves changes

GEC
CM
within CM's delegated

Services



authority


GEC: Responds to RFIs



and reviews submittals















RFIs &
RFCs



Submittals


Construction
Contractor
Contractor
Contractor
Contractors
1
2
3

Contractors: Submit RFIs,


submittals, and RFC to CM





Division of Management Responsibilities between the Agency and Construction Manager

The Project manager is the Relevant body’s  senior decision maker on the project and should be delegated that 

commensurate decision making authority. Where the Relevant body’s  governance policy requires actions to be 

approved by the Relevant body’s  board, the PMP and Agency administrative procedures should not unduly 

delay the construction schedule.

 Figure 6-2, identifies generally accepted divisions of functions between the Agency, CM, and GEC during

 construction.
                           
Figure 6-2 – Agency and Construction Manager Functions During Construction









 Contract Management and Administration

The RE, who is typically a member of the CM staff, oversees the contractor with respect to what work is to be done pursuant to the contract specifications. The RE is the Relevant body’s  primary field representative and the contractor’s single point of contact. The RE receives/processes contractor RFIs and submittals, has the authority to accept or reject contractor work based on compliance with the contract specifications, receives/processes RFCs, and resolves those changes within the RE’s delegated authority. All changes that affect the design must be approved by the designer of record.

The RE and CA(Contract Administrator) meet with the contractor on a regular basis to assess the contractor’s progress. At these meetings the contractor reports on progress, issues that arise in the field are addressed, and any disputes resolved. If disputes cannot be resolved between the RE and contractor they are passed up the project management chain of command as delineated in the PMP.


Value Engineering Changes

The project manager’s responsibility to find VE opportunities – to deliver a better and/or lower cost project without compromising quality – does not end with design.

Even though VE’s main use is in the design phase, the project manager can organize a ―design scrub workshop with the designer and contractor before the start of construction, where the contractor can bring questions, comments, and ideas.



Schedule Control

Construction contractors control their contracts’ detailed schedule progress.The project manager’s focus is the big picture, the master schedule, to manage interfaces between contractor, third party, and Agency construction activities. The Project manager’s approach to master schedule control depends on the project’s size and complexity:

§    For larger and more complex projects Project Manager will require the CM to provide a scheduler to monitor construction progress using scheduling software(Like Microsoft Project) to maintain a master schedule of construction activities.
§    For smaller projects the use of hand drawn bar charts worked out directly with the RE(s) should be adequate to serve as a master schedule for project manager to oversee construction progress. 

Large or small, to control the project schedule the project manager should:


(a)      Create a high-level master schedule and limit detail to what is necessary to control interfaces.

(b)      Focus management on the critical path activities that determine the overall schedule duration.


(c)   A revised baseline schedule for Agency approved contract changes.                                           




Use contractor submission to update the master schedule and focus management effort on
 changes to thecritical path through construction.


Contractor activities forecast to be late that impact the                  critical path
o   Interface activities forecast to be late that impact a contractor’s progress
      o    Validation of progress on activities that control contract milestone payments.


Incorporate into contract conditions schedule milestones for work critical to project completion and/or 

interfaces with other contractors, including liquidated damages for late performance. 



Management techniques for project manager to make timely, decisive, and equitable decisions on RFCs include:

§  Delegate through the project chain of command responsibility and financial authority to make decisions on contract changes.
§  Use a change control board made up of senior project staff to make decisions on large, complex, and/or contentious contract changes.

§  Include within the construction budget a reserve to cover construction risks assumed by the Agency that could result in contract changes.


* Establish up-front through the partnering process an understanding with the contractor of the process for               resolving RFCs, including a disputes resolution process. 

Document Control

Document control is the management of records generated during construction. In addition to the records 

associated with changes, RFIs, and submittals, document control procedures are needed to handle reporting of 

construction progress including:






-Site records that include a daily log of site activities, occurrences, weather, equipment, personnel, and communications.


-Inspection Report of contractor’s work and practices observed by the CM’s construction inspectors covering construction work performed, instructions given or received, unsatisfactory conditions, delays encountered, manpower and equipment, or other problems.

-RE’s weekly Construction Report of all items of importance, conferences with the contractor or other parties, agreements made, special notes regarding equipment or organization, labor conditions, weather or other causes of possible delays, and other matters that have a bearing on the history of the job.

  # Safety management and accident reports.

   # QA/QC reports.


Although communications management is usually thought of as managing damage control when bad things 

happen, communications management also manages good news on the project such as:

#      Announcing the project to promote its benefits.                                                                                              
       --  Holding milestone events to celebrate progress such as to unveiling the design of a new facility.

       --- A groundbreaking to mark the start of construction to inaugurating the start-up of a complted facility.


 #  Publicizing any awards or industry recognition achieved by the project or the project team. 



THIRD PARTY COORDINATION

Third Party Work

Third party work involves the relocation or rearrangement of existing facilities that impact project construction

 including:


§    Utilities (electric power, gas, telephone, cable, etc.)

§    Public infrastructure (highways, bridges, streets, sewer, water, etc.)

§    Railroads.

The timing and duration of third party work requires careful negotiation with third parties due to the significant time required for the work. Work by third parties needs to be accomplished early in the project because any delays impact the follow-on contractors with the risk of delaying the overall project and incurring additional costs due to contractor delay claims.

Third Party Agreements

It is imperative that the project manager negotiates and has in place agreements with third parties early in design so the project manager can assess their impact on the overall schedule, the utilities have time to plan and carry out any design required, and the project manager identifies interfaces with other contractors and incorporates them into the contract provisions.


The project manager’s negotiations with third parties should address betterment work that the third party intends to carry out. Betterments are where the third party takes advantage of the relocation to upgrade the relocated facility. The project manager should agree to reimburse the third party only for the cost of relocating the equivalent facility and any additional costs for upgrades should be borne by the third party.


 QUALITY MANAGEMENT

Scope of Quality Management During Construction

Quality management during the construction phase covers:


#     Review of contract documents to verify that quality aspects have been considered

#     Surveillance of construction for adherence to quality requirements

#     In process and receiving point quality inspections

#     Audits of consultant, contractor, and supplier quality programs for adequacy and compliance.

 Contractor’s Role in Quality Management:

Quality is achieved by the contractors performing work in accordance to an approved quality control plan. Construction contractors and suppliers should be required to submit a quality plan appropriate for their scope of work to the Agency for approval.

The contractor controls the quality of deliverables by monitoring and verification against the quality criteria specified in the design documents. The quality control activities include construction site activity, installation, inspection, test, and documentation. Results of inspections and tests are retained by the contractor as objective evidence of acceptability. The contractor turns over the records to the organization as required by the contract documents.


Audits

The Relevant body’s  quality management plan should include a comprehensive program of periodic audits. The audits are to verify that the CM and contractors have effectively implemented and are in compliance with, applicable elements of the quality management plan. Follow-up audits, including re-audit of deficient areas will be conducted to assure that effective corrective action has been taken.


SAFETY MANAGEMENT DURING CONSTRUCTION

Scope of Safety Management

Safety management during construction phase covers:

§    Planning of work to avoid personal injury and property damage

§    Monitoring of work to provide early detection and correction of unsafe practices and conditions

§    Protecting adjacent public and private properties to provide for the safety of the public

§    Providing safety education and incentive programs

§    Complying with  Occupational Health and Safety Acts (OSHA).

Roles of the relevant organization in Safety Management

The Relevant body’s  role is to establish awareness that the prevention of accidents and protection of employees, the public, and property is a top priority. The Agency should have a safety management plan which can be a sub section of the PMP or on larger projects a separate subsidiary planning document. The requirements of the safety management plan should be incorporated as part of the contract documents.


 Roles of the Contractor in Safety Management

Contractors are responsible for having a safety management plan in place and for assuring safety on site, the safe and healthful performance of their work, preventing accidents or damage to adjacent public and private property, and safety training of their employees. When a contractor is advised by the Agency of a safety violation, the contractor should respond in writing and immediately take corrective action as set out in their safety management plan.

Enforcement

Contractors enforce safety by developing a Job Hazard Analysis for the work to be undertaken and discussing actions needed to provide safety at jobsite planning meetings. Supervisors draw on their safety experience to direct the actions of those under their direction. Contractor staff should include a safety professional who undertakes surveillance of operations to eliminate sources of potential accidents.

Education

Contractors give newly employed, promoted, and/or transferred personnel comprehensive safety indoctrination on topics such as: workplace hazards, required protective equipment, procedures for reporting unsafe job conditions, procedures for reporting accidents, contractor job rules, location of first-aid and medical facilities, and tool box safety meeting requirements.

Foremen or shift supervisors should also hold regular crew training (toolbox) meetings to cover specific safety procedures pertinent to the crew’s on-going activity.

Incentives

Contractors should display signs and posters at the job site to reinforce safety training and as an incentive to maintain interest in job safety with the changing work assignments and jobsite conditions. The Organization should encourage contractors to introduce employee incentive programs that reward safe work performance through personal recognition and prizes such as belt buckles, pins, or lunch boxes.

Accident Investigation and Record Keeping

Accidents should be investigated without delay by the contractor and the investigation should generate recommendations for corrective actions to prevent recurrence of similar accidents. The contractor’s accident report, project records, progress reports, and daily time reports may become important evidential material in any ensuing legal action. 



                                                 (End of Chapter)




Comments