CHAPTER-05
(Management Of Project
Design)
(Inclusion of Green
Building)
Introduction
During
the design phase,importance of the translation of project requirements into
detail drawings and specifications which is required for the construction
contract documents.The key points regarding the translation of preliminary
engineering and final design, managing the project schedule and performing
constructability, value engineering (VE), Quality control (QC) and quality
assurance (QA) throughout development is
important.
Design Phase
The
design phase takes the project requirements through design criteria and
conceptual design to the final design and construction documents for a
contractor to bid on.The design sub-phases, alternatives analysis, conceptual
design,and preliminary engineering – are all interrelated with the
environmental clearance and process.analysis,
Role
of Project Manager:
§ Review and approve
design concepts, preliminary engineering, and final engineering
§ Provide and
coordinate design review comments
§ Participate in Value
Engineering (VE) and risk assessment sessions
§ Manage the design
consultant’s efforts
§ Monitor design costs
and schedule
-
Oversee QA
-
Approve
baseline capital cost and schedule.
Role of design consultant:
(a) Establish
design criteria assess and address project risk.
(b) Perform
conceptual design and preliminary engineering in support of the environmental
clearance document.
(c) Perform technical
studies, develop engineering criteria, and conduct VE and risk assessment.
(d) Estimate capital cost and
construction schedule throughout the design process.
(e) Develop and apply internal QA/QC
criteria for the review of deliverables.
(f) Update capital cost estimates and
construction schedule throughout the design process.
(g) Produce final design drawings and specifications for
the construction bid package.
Design Criteria: The design team will develop
the criteria for the project based on the scope of work provided.Engineering
analysis will establish a range of acceptable criteria or standards of project.
Conceptual
Design – The design consultant will develop graphic plans based
on functional requirements and safety as identified for the preferred
alternative.In addition,they will analyze the project site (s) to determine the
initial “look and feel” of the project once completed.The result of the
conceptual design is a set of architectural plans,elevations,landscaping plan ,
site boundary, and topographic surveys.Depending on the site complexity the
design may include other drawings such as grading,utility,and drainage plans.
VALUE
ENGINEERING
Agencies are encouraged to apply VE techniques to all projects.
The objective of VE is to satisfy the required functions of the project at the
lowest initial total cost and cost over the life of the project. Figure 5-3
provides an overview of the VE process.
Time of Performance Value
Engineering
VE for a project should be
performed early in the design process before major decisions have been
completely incorporated into the design, including civil, systems, and
architectural areas. Ideally, the project manager or the design manager will
see that the VE is accomplished at or prior to the end of preliminary design.
The Procedure to Perform
Value Engineering
The
project manager have to coordinate the VE session that will consist of a
multi-disciplined team of professionals, who preferably are not part of the
design team. VE personnel can include electrical, mechanical, civil/structural,
and construction engineers, as well as specialists in architecture, cost
estimation, construction management, and transit O&M.
CONSTRUCTABILITY REVIEWS
Later in the design process, the design team will need to
perform constructability reviews as part of the design process. Participants
for constructability reviews can come from within your Agency, the design team,
or assistance can be obtained from other transit agencies, code officials,
independent consultants, or contractors.
* Eliminate construction requirements that
are impossible or impractical to build.
* Maximize constructability, recognizing the availability
and suitability of materials, the capability of labor resources, and the
standards of practice of the construction resources.
* Verify accurate depictions of site conditions with regard
to access, utilities, and general configuration.
* Make sure of the adaptation of designed
structures and features to the project site conditions and constraints.
* Determine adequacy of work and storage
space including contractor access to the site.
* Determine appropriate construction
durations and milestones.
* Verify requirements for QA/QC during
construction.
* Clearly define procedures for scheduling
outages and the feasibility of utility interruptions.
* Determine requirements for
Agency-provided materials, equipment, services, and utility connections.
* Make certain that designs can be
constructed using methods, materials, and equipment common to the construction
industry.
* Pay attention to the requirements of the
public including adjacent land use functions, existing transit patrons, and
persons with disabilities.
* Make sure coordination is included with
all operating elements of the existing transit system.
* Make certain adequate provisions are
provided for access, staging, and storage of waste and supplies;
parking for
worker and construction vehicles; and mitigation of environmental impacts
during construction.
RISK ASSESSMENT
Ø Project
risk is an unexpected event or circumstance that has a chance of occurring and
that may prevent aproject from meeting its schedule and cost estimate/budget.
Ø Project
risks can be divided into two main categories: design/construction risks and
financial risks.
ØDesign/construction risks include
weather conditions, contractors' inability to carry out the project, unforeseen
site conditions, permitting delays, and so forth.
ØFinancial risks include revenue
shortfalls, changes in the project cash demands, and changes in interest
rates,among other things.
ØRisk is defined in terms of an event (what may occur to
the detriment of the project),its probability(how
likely it is to occur),and
the amount involved.
Examples
of risks that the Agency project manager and the design consultant should
consider for the project
include:
•
|
Real Estate
|
•
|
Historical
Significance
|
|||||
–
|
Property
Acquisition
|
–
|
Protected Lands
|
|||||
–
|
Relocation
|
–
|
Archaeological
|
|||||
–
|
Condemn
|
–
|
Structures
|
|||||
–
|
Eminent Domain
|
• Contract phasing and packaging
|
||||||
•
|
Public Utilities
|
–
|
Scope of Work
|
|||||
–
|
Analysis and
Coordination
|
–
|
Bid Process/Labor
|
|||||
–
|
Agreements
|
–
|
Integrating
Construction Packages
|
|||||
–
|
Relocation
|
• Community impacts and public perception
|
||||||
•
|
Financial
|
•
|
Public hearing
|
|||||
•
|
Politics
|
–
|
Marketing/Communication
|
|||||
–
|
Internal/External
|
–
|
Safety and Security
|
|||||
•
|
Environmental
|
• Material, Equipment and Construction
|
||||||
–
|
Environmental
Impact Studies
|
Techniques
|
||||||
QUALITY ASSURANCE AND QUALITY CONTROL:
Quality Assurance & Quality Controll Oversight
The QA/QC plan is set in
place for the design portion of the project. The plan should answer the
questions of who is responsible and when in time actions should occur. More
important, the quality plan needs to be maintained throughout the design phase
so that as a new phase is initiated, it will reflect the appropriate quality
requirements.
Quality Control – the act of taking
measurements, testing, and inspecting a process or product to make sure that it
meets specification. It also includes actions by those performing the work to
control the quality of the work. Products may be design drawings or
specifications, manufactured equipment, or constructed items. Quality Control
also refers to the process of witnessing or attesting to, and documenting such
actions.
Quality Assurance –
making certain the project requirements are developed to meet the needs of all
relevant internal and external agencies, planning the processes needed to
assure quality of the project, making sure that equipment and staffing is
capable of performing tasks related to project quality, making sure that
contractors are capable of meeting and do carry out quality requirements, and
documenting the quality efforts.
SUSTAINABILITY (GREEN
BUILDING) STANDARDS AND DESIGN
The Concept of Green Building Design:
Green building design can be
thought of as the intelligent integration of technology with nature. The primary objectives are:
§ Energy: Reduce energy consumption and operational
costs.
§ Materials: Maximize the use of sustainable materials.
§ Air
Quality: Minimize negative impacts on
interior air quality.
§ Productivity: Improve the health, motivation and
productivity of human occupants.
Sustainability
design features can range from simple conservation features, such as the
incorporation of low-
flow water fixtures and occupancy sensing light switches;
to more high-end systems like geothermal heat
pumps, solar electric panels,
wind turbines, and vegetated roofs.
Reason
for Considering Green
Building Design?
The built environment has a
profound impact on our natural environment, economy, health, and productivity:
Benefits
of Green Building
o
Environmental:
§ Enhance
and protect ecosystems and biodiversity
§ Improve
air and water quality
§ Reduce
solid waste
§ Conserve
natural resources
o Economic:
§ Reduce
operating costs
§ Enhance
asset value and profits
§
Improve employee productivity and
satisfaction
§
Optimize life-cycle economic performance.
o Health and Community:
§ Improve
air, thermal, and acoustic environments
§ Enhance
occupant comfort and health
§ Minimize
strain on local infrastructure
§ Contribute
to overall quality of life
- Sustainable Sites
- Water Sites
- Water Efficiency
- Energy & Atmosphere
- Indoor Environmental Quality
- Innovation & Design Process
- Regional Priority
SUSTAINABILITY DESIGN CONCEPTS
The design process should include:
* Design Charretes :used to set project goals including environmental goals.
* Site selection & how to use site sustainably.
* Evaluation of existing building reuse.
* Energy Modeling:used to provide most energy efficient building that meets the most energy efficient budget.
Energy efficiency Analysis to evaluate.
Building Envelop
HVAC system
Lighting System
Sustainable material selection:
Recycled Content
Recyclability
Local Materials.
Low volatile Organic Compound.(VOC)
Commissioning to of all system to ensure proper installation & operation of all building system.
(End of Chapter)
---------------
---------------
Comments
Post a Comment